Regeneration programme


The Aylesbury regeneration area will be in transition for nearly 20 years. It’s difficult to process the idea of change over such a long time frame so we’ve created a visual timeline. The timeline shows progress and timescales for change to help you understand what is happening near you and when.

 

Regeneration Commences

 
 

L&Q Site 1a

Completed
2011/12

 
 
 

L&Q Site 7

Complete
2016

 
 
 

First Development Site

Rehousing: 2013 - 2018
Consultation: 2014 - 18
Soft strip demolition started: Summer 2015
Main demolition started: January 2016
First new homes: Summer 2020
First Development Site complete: Winter 2023

 
 
 

Introduction Exhibition

March 2014

The first exhibition was timed to correspond with the Creation Trust Annual General Meeting. The boards presented information on the design team's response to the AAAP, precedent images for the buildings and...

 Read more »

 
 
 

1-2-1 Meetings

May - July 2014

Interviewed residents to help us to get a basic understanding of the issues.

 
 
 

Visit to other Notting Hill Developments

May 2014

Residents visited three other NHH developments to get an idea of the style and quality of their properties.

 
 
 

Vision Workshop

May 2014

We introduced our team, and the masterplan design principles that will underpin the proposed design of the whole site. Public workshops explored the design principles in greater detail, looked at ideas about...

 Read more »

 
 
 

Masterplan Evolution

19 - 21 June 2014

We presented the draft masterplan for the whole estate and detailed designs for the First Development Site. This showed how the design principles have been incorporated into the plan. The workshop was a chance...

 Read more »

 
 
 

Walk & Talks

June 2014

Led by residents to help us gain insight into the area.

 Read more »

 
 
 

Final Exhibitions Before Planning Submission

13-14, 30 August 2014

These exhibitions will present the plans that will be submitted for planning permission. We will also set out the plan for the ongoing consultation and engagement across the next stages of the regeneration, as...

 Read more »

 
 
 

Planning Submission

October 2014

The regeneration of the Aylesbury estate has moved another step closer after Notting Hill Housing (NHH) submitted its planning proposals to Southwark Council. If given the green light, the proposals will...

 Read more »

 
 
 

Temporary Project Office

February 2015

A temporary office for the Aylesbury project team to operate from an existing space within the estate.

 
 
 

Planning Approval

24 April 2015

The regeneration took a huge step forward after planning permission was granted by Southwark Council.

 Read more »

 
 
 

Designing a new public square

7 March 2015

Public consulation for shaping the design of the new public square and surrounding community buildings that will sit in the heart of the new neighbourhood.

 Read more »

 
 
 

Demolition

Summer 2015

Pre-demolition works on the First Development Site Summer 2015

 
 
 

Co-design of Community Hub

Summer 2015

Work with local people to design a community hub.

 
 
 

East Street library is moving

16 September 2015

We really want to hear your ideas for shaping the design of the new public library that will sit in the heart of the new neighbourhood.

 Read more »

 
 
 

New public square exhibition

26 September 2015

We really want to hear your ideas for shaping the design of the new public square and surrounding community buildings that will sit in the heart of the new neighbourhood.

 Read more »

 
 
 

Public square final exhibition

17 October 2015

We really want to hear your ideas for shaping the design of the new public square and surrounding community buildings that will sit in the heart of the new neighbourhood.

 Read more »

 
 
 

Theme Groups

Early 2016

For people interested in specific aspects of the regeneration, eg: open spaces, community project.

 
 
 

Plot 18 consultation event

23 January 2016

Come and see updated designs for the new neighbourhood hub and community facilities. We want to know what you think!

 Read more »

 
 
 

Planning Application for Plot 18

07 July 2016

Following further consultation around the different elements that make up plot 18 we will submit the detailed designs for this new neighbourhood hub with a view to achieving planning approval early in 2016.

 

First Development Site Complete Winter 2023

 
 
 
 
 

Phase 2 (inc. Plot 18)

Rehousing: 2014-2019
Consultation: 2015/16
First Phase 2 Homes: Summer 2020
Phase 2 Complete: 2025

 
 
 
 
 

Phase 3

Rehousing: 2018-2021
Consultation: 2019/20
First Phase 3 Homes: End 2024
Phase 3 Complete: 2027

 
 
 
 
 

Phase 4

Rehousing: 2020-2027
Consultation: 2021
First Phase 4 Homes: Summer 2027

 
 

Regeneration Complete
2036





The information on this page was updated in May 2018. Please note that the regeneration is a long-term project so timelines may change over time.